Strengthening a Fragile Power System After Hurricane Maria
Following the devastation of Hurricane Maria, Puerto Rico faced one of the most significant power crises in its history. The island’s ageing electrical infrastructure, much of it originally commissioned in the 1960s and 1970s suffered extensive damage, resulting in widespread outages and long-term instability.
To restore dependable power generation and improve system resilience, New Fortress Energy deployed multiple mobile gas turbine units across Puerto Rico. ESS was selected to provide full installation, commissioning, and ongoing operational support for this critical project.
Across two major sites, ESS helped bring 17 gas turbines online, bolstering energy security during a period of urgent need and laying the foundation for long-term grid stability.
ESS provided a complete turnkey service covering installation, commissioning, operations, and technical support.
Installation & Commissioning of 17 Gas Turbines
Our engineers managed all aspects of turbine readiness, including:
ESS ensured every turbine met OEM standards and local regulatory requirements, delivering reliable generation capacity to the island’s grid.
18-Month Operation & Maintenance Support
Following successful commissioning, ESS provided an on-site Operations & Maintenance (O&M) team for 18 months, ensuring stable, safe, and continuous operation of the installed fleet.
Our O&M support included:
This long-term presence ensured continuous reliability throughout Puerto Rico’s recovery and rebuilding period.
24/7 On-Call Technical Expertise Across the Island
Beyond the new installations, ESS provided round-the-clock support for all electrical assets connected to the project, including legacy equipment at sites originally commissioned in the 1960s and 1970s.
Our technical specialists supported:
This required a deep understanding of both modern and legacy power-generation technologies, an area where ESS excels.
Puerto Rico’s unique conditions presented several challenges:
ESS maintained a disciplined, safety-first approach while delivering reliable, high-quality technical solutions under difficult circumstances.
Throughout the project, ESS maintained its excellent safety record by implementing:
Despite demanding environments and deteriorated legacy equipment, ESS achieved zero lost-time incidents (LTIs) over the full duration of the project.
The deployment and long-term support of the 17 gas turbines significantly strengthened Puerto Rico’s power grid during a period of critical recovery.
ESS delivered:
Full installation & commissioning across two major sites
ESS played a key role in restoring and stabilizing power across Puerto Rico, ensuring that critical facilities and communities had access to dependable electricity during the island’s post-disaster recovery.
The Puerto Rico project showcases ESS’s ability to deliver large-scale, mission-critical engineering under extremely challenging conditions. Our combination of technical depth, rapid response, and long-term operational support helped restore power, stabilise an ageing network, and provide the island with the dependable generation capacity it urgently needed.
ESS continues to support global power-restoration efforts where reliability, speed, and safety are paramount.
© Energy Specialist Solutions | An Energy Services Company | Privacy Policy